Which process ensures that provision has been made to address any open issues of risks, with follow-on action recommendations?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

Which process ensures that provision has been made to address any open issues of risks, with follow-on action recommendations?
A . Closing a Project
B . Controlling a Stage
C . Directing a Project
D . Initiating a Project

Answer: A