Which Process Group and Knowledge Area include the Sequence Activities process?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Which Process Group and Knowledge Area include the Sequence Activities process?
A .  Executing Process Group and Project Time Management
B .  Executing Process Group and Project Cost Management
C .  Planning Process Group and Project Time Management
D .  Planning Process Group and Project Cost Management

Answer: C