Which process involves determining, documenting, and managing stakeholders’ needs and requirements to meet project objectives?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Which process involves determining, documenting, and managing stakeholders’ needs and requirements to meet project objectives?
A .  Collect Requirements
B .  Plan Scope Management
C .  Define Scope
D .  Define Activities

Answer: A