Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?
A .  Estimate Costs
B .  Control Costs
C .  Determine Budget
D .  Plan Cost Management

Answer: B