Which process numerically analyzes the effect of identified risks on overall project objectives?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Which process numerically analyzes the effect of identified risks on overall project objectives?
A .  Plan Risk Management
B .  Plan Risk Responses
C .  Perform Quantitative Risk Analysis
D .  Perform Qualitative Risk Analysis

Answer: C