Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?
A .  Critical path method
B .  Critical chain method
C .  Resource leveling
D .  Schedule network analysis

Answer: B