Posted by: Pdfprep Category: PRF Tags: PRF exam questions, PRF practice exam, PRINCE2 Foundation Post Date: November 15, 2020 Pdfprep2020-11-15T22:16:05+00:00 Which should be provided by a project mandate?A . Terms of referenceB . Detailed Business CaseC . Stage tolerancesD . Initiation Stage Plan View Answer Answer: A Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.