After an SRDF failover operation, production work has been moved to the remote site. A large number of invalid tracks have accumulated that need to be synchronized back to the R1 volumes.

Which SRDF operation can reduce the re-synchronization time, while continuing production work on the remote site?
A . Update
B . Failback
C . Restore
D . Establish

Answer: A