Which statement about standard changes is CORRECT?

Posted by: Pdfprep Category: ITILFND_V4 Tags: , ,

Which statement about standard changes is CORRECT?
A . A full assessment should be completed each time the change is implemented
B . The change can be implemented with less testing if necessary
C . The appropriate change authority should be assigned to each type of change
D . The change does not require additional authorization

Answer: D