Which time elements can be reduced by a reduction strategy? Note: There are 3 correct answers to this question.

Posted by: Pdfprep Category: C_TS422_2020 Tags: , ,

Which time elements can be reduced by a reduction strategy? Note: There are 3 correct answers to this question.
A . Wait time
B . Goods receipt processing time
C . Float after production
D . Queue time
E . Move time

Answer: C,D,E