PdfPrep.com

Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements? Note: There are 2 correct answers to this question.

Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements? Note: There are 2 correct answers to this question.
A . Total replenishment lead time
B . Operation duration
C . In-house production time
D . Planned delivery time

Answer: C,D

Exit mobile version