While planning for the data migration, what techniques should the Architect recommend to make sure the load go according to schedule?


Universal Containers has decided that they will be using the bulk API to migrate the existing data into Salesforce as they will be importing a total of 80 million records.

While planning for the data migration, what techniques should the Architect recommend to make sure the load go according to schedule? Choose 2 answers
A . Pre-process data that the triggers and workflows can be deactivated.
B . Perform a test load using a full Sandbox prior to the Production load.
C . Perform loads over a weekend server resource availability.
D . Leverage several workstations, loading different objects simultaneously.

Answer: A,B