Whose responsibility is it to assure the project’s stakeholders that the project remains desirable, viable and achievable at all times?

Whose responsibility is it to assure the project’s stakeholders that the project remains desirable, viable and achievable at all times?
A . Project Manager
B . Corporate or programme management
C . Senior User
D . Executive

Answer: D