You are a functional consultant for Contoso Entertainment System USA (USMF)

SIMULATION

You are a functional consultant for Contoso Entertainment System USA (USMF).

You need to schedule the Material Requirements Planning (MRP) master plan to run nightly at 03:00 (UTC-8).

To complete this task, sign in to Dynamics 365 portal.

Answer: You need to configure a batch job to run the master plan nightly.

Create the batch job

Exit mobile version