You are the new Scrum Master at a company currently doing RUP in three month iterations. Your current task in switching from RUP to Scrum is to define how long the Sprint cycle should be. In what units of time should you define the sprint cycle?

Posted by: Pdfprep Category: CSM-001 Tags: , ,

You are the new Scrum Master at a company currently doing RUP in three month iterations. Your current task in switching from RUP to Scrum is to define how long the Sprint cycle should be. In what units of time should you define the sprint cycle?
A .  A fixed amount of months
B .  A fixed amount of weeks, excluding holidays
C .  A fixed amount of days
D .  A fixed amount of hours

Answer: C