You create a maintenance order with header-based costing. At which level can the planner display the expected costs? (Choose two.)

Posted by: Pdfprep Category: C_TS413_1809 Tags: , ,

You create a maintenance order with header-based costing. At which level can the planner display the expected costs? (Choose two.)
A . At the cost element level
B . At the work center level
C . At the component level
D . At the value category level

Answer: AD