According to PRINCE2, which of the following are the aspects of project performance to be managed?

According to PRINCE2, which of the following are the aspects of project performance to be managed?
A . Processes, themes, principles
B . Time, cost, quality, people
C . Time, cost, quality
D . Time, cost, quality, scope, benefits, risk

Answer: D