PdfPrep.com

After analyzing a set of requirements documents, it is determined that the requirements are not yet ready for peer review.

After analyzing a set of requirements documents, it is determined that the requirements are not yet ready for peer review.

This was most likely caused by:
A . the requirements not providing all of the information needed to define the work.
B . the requirements documents having not yet received sign-off from the sponsor.
C . the requirements’ reference codes not tracing to the attribute numbers in the work breakdown structure.
D . some requirements having not yet been discussed in a work group session.

Answer: A

Exit mobile version