What would have helped determine this issue before delivery?

Posted by: Pdfprep Category: PMI-PBA Tags: , ,

After a project was delivered, the business analyst learns of a project objective with no associated requirement.

What would have helped determine this issue before delivery?
A . Use cases
B . Process flow
C . Context diagram
D . Tracing requirements

Answer: D