In which ADM phase is the Implementation and Migration Plan coordinated with other activities in the enterprise?

In which ADM phase is the Implementation and Migration Plan coordinated with other activities in the enterprise?
A . Phase A
B . Phase G
C . Phase E
D . Phase H
E . Phase F

Answer: E

Explanation:

Reference https://pubs.opengroup.org/architecture/togaf91-doc/arch/chap14.html