In which ADM phase is the Implementation and Migration Plan coordinated with other activities in the enterprise?
A . Phase A
B . Phase G
C . Phase E
D . Phase H
E . Phase F

Answer: E

Explanation:

Reference https://pubs.opengroup.org/architecture/togaf91-doc/arch/chap14.html