Which of the following activities is NOT an action of preparing for planned closure?

Which of the following activities is NOT an action of preparing for planned closure?
A . Update the project plan with actual
B . Update the Project Management Team
C . Request a product status account
D . Confirm project has delivered what is defined in Project Product Description

Answer: B