Is the team manager’s response appropriate, and why?


The project is at the start of stage 3, and there will be six teams working on product delivery. In order to exercise control, the project manager has asked each team to submit a detailed team plan for approval. The external team manager for the ‘e-learning course’ has agreed to submit a summary to the project manager, but will submit the detailed team plan to the senior supplier to review and approve.

Is the team manager’s response appropriate, and why?
A . Yes, because a supplier may want to keep the details of the specialist work confidential.
B . Yes, because team plans are mandatory on a project of this size and complexity.
C . No, because the project manager needs detailed plans to manage the work of several teams.
D . No, because the team plan must be submitted to project assurance to check it is viable.

Answer: A

Leave a Reply

Your email address will not be published.