Which of the following is a key aspect of the Agile project management methodology?

Which of the following is a key aspect of the Agile project management methodology?
A . Test-driven
B . Daily standup meetings
C . Short project durations
D . Defined list of requirements

Answer: B

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 286