In a Scrum retrospective, which of the following categories are used to classify the feedback from the team?

Posted by: Pdfprep Category: PK0-004 Tags: , ,

In a Scrum retrospective, which of the following categories are used to classify the feedback from the team?
A . Direct and indirect
B . Pros and cons
C . Pluses and minuses
D . Likes and dislikes

Answer: C