Which of the following must be included in the risk register when the project manager completes the Identify Risks process?

Which of the following must be included in the risk register when the project manager completes the Identify Risks process?
A . List of identified risks, potential risk owners, list of potential risk response
B . List of identified risks, list of causes, list of risk categories
C . Short risk titles, list of potential risk owners, list of impacts on objectives
D . List of activities affected, list of potential risk responses, list of causes

Answer: A