Which of the following must be included in the risk register when the project manager completes the Identify Risks process?

Posted by: Pdfprep Category: CAPM Tags: , ,

Which of the following must be included in the risk register when the project manager completes the Identify Risks process?
A . List of identified risks, potential risk owners, list of potential risk response
B . List of identified risks, list of causes, list of risk categories
C . Short risk titles, list of potential risk owners, list of impacts on objectives
D . List of activities affected, list of potential risk responses, list of causes

Answer: A

Leave a Reply

Your email address will not be published.