Posted by: Pdfprep Category: PSM I Tags: PSM I exam questions, PSM I practice exam, Scrum Certification Post Date: March 10, 2021 Pdfprep2021-03-10T14:21:05+00:00 Who is responsible for managing the progress of work during a Sprint?A . The Scrum Master.B . The Development Team.C . The Product Owner.D . The most junior member of the Team. View Answer Answer: B Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.