Posted by: Pdfprep Category: CAPM Tags: CAPM exam questions, CAPM practice exam, CAPM Certification Post Date: November 26, 2020 Pdfprep2020-11-26T16:36:44+00:00 Which of the following tasks focuses on decomposing work packages?A . Adjust duration estimatesB . Define activitiesC . Complete rolling wave planningD . Develop milestone list View Answer Answer: B Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.