Posted by: Pdfprep Category: PRINCE2 Tags: Polycom Certification, PRINCE2 exam questions, PRINCE2 practice exam Post Date: November 1, 2020 Pdfprep2020-11-01T23:48:24+00:00 What is used to pass responsibility to a Team Manager for the production of one or more products?A . Exception PlanB . Work PackageC . Product DescriptionD . Checkpoint Report View Answer Answer: B Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.