Posted by: Pdfprep Category: PRINCE2 Tags: Polycom Certification, PRINCE2 exam questions, PRINCE2 practice exam Post Date: November 6, 2020 Pdfprep2020-11-06T23:03:56+00:00 Enables the project manager to have complete autonomy over the products to be producedA . 1, 2, 3B . 1, 2, 4C . 1, 3, 4D . 2, 3, 4 View Answer Answer: A Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.