Posted by: Pdfprep Category: PRINCE2 Tags: Polycom Certification, PRINCE2 exam questions, PRINCE2 practice exam Post Date: October 21, 2020 Pdfprep2020-10-21T11:26:37+00:00 Who determines the use of a change authority and change budget during project initiation?A . Project BoardB . Senior UserC . Project ManagerD . Corporate or Programme Management View Answer Answer: A Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.