Posted by: Pdfprep Category: PRINCE2 Tags: Polycom Certification, PRINCE2 exam questions, PRINCE2 practice exam Post Date: December 5, 2020 Pdfprep2020-12-05T18:26:44+00:00 Which role is responsible for ensuring that the expected benefits are realized?A . Project ManagerB . Project AssuranceC . Senior UserD . Executive View Answer Answer: C Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.