Posted by: Pdfprep Category: PRINCE2 Tags: Polycom Certification, PRINCE2 exam questions, PRINCE2 practice exam Post Date: October 21, 2020 Pdfprep2020-10-21T13:15:52+00:00 Which PRINCE2 role has a specific responsibility for planning, monitoring and managing the team’s work?A . Senior SupplierB . Project SupportC . Team ManageD . Project Manager View Answer Answer: C Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.