Posted by: Pdfprep Category: PMI-001 Tags: PMI Certification, PMI-001 exam questions, PMI-001 practice exam Post Date: October 25, 2020 Pdfprep2020-10-25T20:16:03+00:00 Which output is the approved version of the time-phased project budget?A . Resource calendarB . Scope baselineC . Trend analysisD . Cost baseline View Answer Answer: D Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.