During a monthly executive steering committee meeting, a functional manager states that they have not been made aware of the schedule delays documented in the last status report.
What should the project manager do to avoid this situation in the future?
A . Provide the functional manager with access to the project management information system (PMIS).
B . Update the risk register to reflect a possible project interruption caused by the functional manager.
C . Conduct a regular project team meeting to highlight status, issues, and risks before reporting to the steering committee.
D . Update the schedule, lessons learned, and issue log prior to the next steering committee meeting.
Answer: D