To avoid stakeholder frustration, what should the project manager have done?

Posted by: Pdfprep Category: PMP Tags: , ,

One week after project deployment, a project manager unsuccessfully tries to resolve an issue on their own. The project manager failed to inform stakeholders, which resulted in their frustration.

To avoid stakeholder frustration, what should the project manager have done?
A . Referenced the lessons learned repository
B . Updated the issue log
C . Adhered to the communications management plan
D . Referred to the stakeholder engagement

Answer: B