The communication technology being applied in a project was tested in simulated environments but never in actual projects. This lack experience with the technology must be addressed in detail.
Which at the following strategies should be used in the project’s planning process?
A . Provide a status update to senior management
B . Update the project scope if the project grows more complex
C . Mitigate the risk by conducting a pilot
D . Exploit the threat by using an alternative technology.
Answer: C