A project manager assumes a new project.
As part of the initiation process, what should the project manager do prior to the planning stage?
A . Define the project sign-off criteria and create a risk register
B . Start gathering requirements and plan the kick-off meeting.
C . Develop the project charter and identify the stakeholders
D . Acquire the resources and determine the budget
Answer: C