What document can the project manager share with the senior manager to enforce their authority to obtain resources?

Posted by: Pdfprep Category: PMP Tags: , ,

A company’s senior manager is expected to supply dedicated resources for a project However, the project manager has yet to receive the names of these resources

What document can the project manager share with the senior manager to enforce their authority to obtain resources?
A . Project training plans
B . Project charter
C . Project schedule
D . Project management plan

Answer: D