What should the project manager do next?

Posted by: Pdfprep Category: PMP Tags: , ,

A project is completed and the product design packaging is delivered and accepted by the customer’s design engineer However, customer payment is still unresolved due to a concern about the product’s warranty

What should the project manager do next?
A . Document historical information and lessons learned.
B . Coordinate payment issues with the customer
C . Review the customer acceptance document.
D . Review the contract to ensure that all project requirements are complete

Answer: D