A global technology company invested in an infrastructure upgrade project as a part of its business strategy. During the planning phase, the project team works with stakeholders to identify project requirements. The project manager is having difficulty engaging stakeholders who work internationally in different time zones. The stakeholders are unable to participate in regularly scheduled planning meetings, and often do not provide timely responses to emails and other requests for information.
What should the project manager do next to minimize the impact this issue may have on the project?
A . Create the communications management plan.
B . Create the resource management plan.
C . Alert senior management.
D . Arrange a meeting to discuss the issue.
Answer: A