A project is behind schedule and over budget. The original scope has also changed significantly.
Which activity should be the immediate focus of a newly assigned project manager?
A . Perform a risk analysis to determine if there is a risk of additional cost, scope, and schedule slippages.
B . Freeze the project scope to prevent further scope creep, thereby controlling cost and schedule.
C . Review critical path activities that can be adjusted to shorten the timeframe and reduce expenses.
D . Assess the project based on the original charter, and meet with the sponsor to review the business case.
Answer: A