Which grid shows which resources are tied to work packages?

Posted by: Pdfprep Category: CAPM Tags: , ,

Which grid shows which resources are tied to work packages?
A . Work breakdown structure (WBS)
B . Responsibility assignment matrix (RAM)
C . Project assignment chart
D . Personnel assignment matrix

Answer: B

Explanation:

Responsibility Assignment Matrix (RAM). A grid that shows the project resources assigned to each work package.