A company whose Information Technology (IT) services are being delivered from a Tier 4 data center, is preparing a companywide Business Continuity Planning (BCP).
Which of the following failures should the IT manager be concerned with?
A . Application
B . Storage
C . Power
D . Network
Answer: C