PdfPrep.com

Which option is an appropriate Change Authority for the Outsourcing project?

While preparing the Configuration Management Strategy, the Project Manager considered the options for change control. He decided to recommend a change budget of £250k, but was undecided on the Change Authority to recommend.

Which option is an appropriate Change Authority for the Outsourcing project?
A . The selected service provider to approve and implement all changes.
B . Senior User(s) and Project Assurance representatives, within the limits of the recommended change budget.
C . The Director of Facilities and the Director of Information Technology to approve all changes.

Answer: B

Exit mobile version