Which action should the project manager carry out as part of the ‘update the project plan’ activity?


The project is approaching the end of stage 3, and stage 4 is being planned as part of the ‘managing a stage boundary’ process.

Which action should the project manager carry out as part of the ‘update the project plan’ activity?
A . Include the actual time and cost of the work to prepare the ‘marketing materials’ in the project plan.
B . Ensure that the team manager for the work package ‘delivered pilot courses’ is included as a resource.
C . Update the project’s business case to show any new key risks that have been identified.
D . Include the tolerances for the work package ‘delivered pilot courses’ in the project plan.

Answer: A

Explanation:

Reference: https://www.prince2primer.com/prince2-2017-update-project-plan-business-case/