Which option is an appropriate Change Authority for the Outsourcing project?


While preparing the Configuration Management Strategy, the Project Manager considered the options for change control. He decided to recommend a change budget of £250k, but was undecided on the Change Authority to recommend.

Which option is an appropriate Change Authority for the Outsourcing project?
A . The selected service provider to approve and implement all changes.
B . Senior User(s) and Project Assurance representatives, within the limits of the recommended change budget.
C . The Director of Facilities and the Director of Information Technology to approve all changes.

Answer: B

Leave a Reply

Your email address will not be published.