Which step must an administrator complete to reduce the number of blueprints to provision machines from different OVF or OVA files?

Posted by: Pdfprep Category: 2V0-31.19 Tags: , ,

Which step must an administrator complete to reduce the number of blueprints to provision machines from different OVF or OVA files?
A . Use the datacenter location drop-down.
B . Create blueprints tied to a reservation policy.
C . Create a software component.
D . Use an image value set for a component profile.

Answer: D

Explanation:

Reference: https://usermanual.wiki/Pdf/vrealizeautomation74configuration.975498135/help