According to the waterfall cycle approach to systems development, which of the following sequence of events is correct?

Posted by: Pdfprep Category: IIA-CIA-Part3 Tags: , ,

According to the waterfall cycle approach to systems development, which of the following sequence of events is correct?
A . Program design, system requirements, software design, analysis, coding, testing, operations.
B . System requirements, software design, analysis, program design, testing, coding, operations.
C . System requirements, software design, analysis, program design, coding, testing, operations.
D . System requirements, analysis, coding, software design, program design, testing, operations.

Answer: C